Many public tenders are split into lots: separate contracts for different services, areas or sizes of work. For a small supplier, lots are often the way in, because one regional or specialist lot can be well within reach when the whole contract is not. The skill is choosing the lots you can genuinely win and deliver, rather than bidding for all of them.
Last checked: 8 October 2026
Find tenders for your company
Paste your website and we score this week’s UK public sector tenders against it, each with a reason. Free, no sign-up.
What a lot is
A lot is a part of a procurement that is awarded as its own contract. One tender can contain several lots, and one supplier can win more than one. Buyers commonly split work by type of service (say, cleaning in one lot and window cleaning in another), by geography (north and south of a county) or by size. The government's guidance on lots uses multi-site cleaning as its example: geographic lots can help small firms and make supply more resilient, even where a single national contract might offer economies of scale.
The buyer's duty to consider lots
Under section 18 of the Procurement Act 2023, before publishing a tender notice the buyer must consider whether the goods, services or works could reasonably be supplied under more than one contract, and whether those contracts could appropriately be awarded by lots. If both are true, it must either use lots or give its reasons for not doing so.
For most contracts those reasons go in the tender notice itself (light touch and utilities contracts have more flexibility). The Act does not list acceptable reasons. The guidance gives examples such as splitting the work raising the technical risk to delivery, or several suppliers making the contract disproportionately hard to manage. Reading the reasons is useful: if a buyer has decided against lots because it wants one supplier to manage everything, a partnership or subcontracting route may be your realistic way in.
This sits alongside a wider duty in section 12(4): buyers must have regard to the particular barriers small and medium-sized enterprises face and consider whether they can be removed or reduced. The section 18 duty applies to contracts above the procurement thresholds. For smaller regulated contracts below them, section 86 sets a similar duty to consider barriers for SMEs before inviting tenders, though it does not require lots. Our guide to the Procurement Act 2023 covers the wider changes.
Limits on how many lots you can bid for or win
A buyer has two separate levers, and it must tell you about either in advance:
- A cap on bids. A competitive tendering procedure may limit the number of lots any one supplier can submit a tender for (section 20(7)). The maximum must be in the tender notice.
- A cap on wins. When setting award criteria, the buyer may limit the number of lots any one supplier can be awarded, but it must then provide an objective way of choosing which lots a supplier gets if it would otherwise exceed the limit (section 23(4)). The maximum and that mechanism must be set out in the tender notice or tender documents.
A cap on wins changes your strategy. If you can win at most two lots, bidding for four costs you the effort of four bids for at most two contracts, and the tie-break rule may hand you the two you least wanted. Read the mechanism before you decide which lots to put the most work into.
Bidding for several lots, and combined awards
Award criteria are set for each lot, and each lot goes to the most advantageous tender for that lot. In practice that means each lot is scored on its own. If the questions are the same across lots, tailor the answers anyway: a method statement for a rural lot that talks about city-centre access will lose marks.
The tender notice must say whether the buyer will award multiple lots to the same supplier in accordance with criteria, and summarise those criteria (Procurement Regulations 2024, regulation 18(2)(p)). The guidance adds that a buyer wanting the option to combine several lots into a single contract, where one supplier wins them, must say so in the notice or documents. Some tenders also invite a price for a combination of lots, such as a discount if you win two neighbouring areas. Only offer one if the documents allow it, and make sure each single-lot price still stands on its own if you win just one.
How lots appear in a notice on Find a Tender
The tender notice is the place to start. Under regulation 18 of the Procurement Regulations 2024, where a contract is awarded by lots the notice gives, for each lot, so far as the buyer knows them:
| Field in the notice | Why it matters to you |
|---|---|
| Lot title and number | The reference you use in clarification questions and your response |
| Description, location and dates | Whether the work fits your services and the area you cover |
| Estimated value of the lot | Whether it is in proportion to your turnover and capacity |
| Award criteria for the lot | How you will be scored, which can differ between lots |
| Maximum lots per supplier | Caps on bids, caps on wins, and any rule for awarding several lots to one supplier |
| Suitability for SMEs or VCSEs | Whether the buyer considers a lot particularly suitable for small firms or social enterprises |
Later notices follow the lots through. The contract award notice can cover several lots, and a lot the buyer decides not to award is recorded as a ceased lot. If a lot attracts no suitable tenders, the buyer may award that lot alone directly under section 43 while the other lots carry on (lots guidance). Use the tender finder to search live notices, and the tender glossary for the terms you meet in them.
Lots in framework agreements
Frameworks are commonly divided into lots, by type of work, value band or region. If a framework uses lots, the tender notice must include the estimated value of each lot where known, and the government's frameworks guidance says a published lot estimate cannot then be exceeded, unless the framework is lawfully modified. Getting onto the right lot matters more than getting onto the framework: call-off contracts are awarded under a particular lot, so a place on a lot you rarely use earns you nothing. See framework agreements for how call-offs work.
A worked example
These figures are illustrative. A county council tenders grounds maintenance in four geographic lots (North, South, East and West), each with an estimated value of around £150,000 a year. The notice says a supplier may bid for all four lots but be awarded no more than two, and that if a supplier comes top in more than two, it will be awarded the two lots where its score is furthest ahead of the next bidder.
You are a six-person firm based in the North, with your depot ten minutes from the lot boundary with East. Your turnover is £400,000.
- North is your home ground: you know the sites, you have local references and travel costs are low. Bid, and put your best work here.
- East is next door. Winning it would roughly double the work you do, so check whether you could recruit and equip a second team in time. If you can show how, bid; if not, leave it.
- South and West are an hour away. Your prices would carry travel time your local rivals do not, and the cap means winning them could cost you North or East under the tie-break rule. Do not bid.
Two well-made bids beat four rushed ones. Our bid or no-bid guide and before you bid checklist help with the capacity and evidence questions, and writing a tender response covers the answers themselves.
Procurements still under the old rules
Procurements started under the Public Contracts Regulations 2015, and call-offs from frameworks set up under them, continue under those rules (Cabinet Office transparency guidance). Regulation 46 of the 2015 rules worked in a similar way: buyers could cap the lots one tenderer could win, set objective rules for allocating them, and combine lots only if the contract notice reserved that option.
Before you choose your lots
Read the lot descriptions, the caps on bids and wins, and the rule for allocating lots, then bid only where you have a real edge in location, experience or price. A lot you cannot staff is a contract you do not want to win.
Find the lots that fit you
Tender Radar reads every new UK public sector notice, scores it against what you do and emails you the ones worth reading, so a lot that suits you is not buried in a big tender. 30 days free, no card needed.
Common questions
Lots in public tenders
What is a lot in a public tender?
A lot is a separate part of a larger procurement that is awarded as its own contract. A buyer might split a requirement by service, by geography or by value, so that different suppliers can win different parts. Each lot has its own description, estimated value and award criteria in the tender notice.
Does a buyer have to split a contract into lots?
Not always. Under section 18 of the Procurement Act 2023 the buyer must consider whether the work could reasonably be split into several contracts awarded by lots. If it could, the buyer must either use lots or give its reasons for not doing so. For most contracts those reasons appear in the tender notice.
Can I bid for more than one lot?
Usually, yes. But the buyer can limit how many lots one supplier may bid for, and separately how many lots one supplier may win. Any limit must be stated in the tender notice, and a limit on wins must come with an objective way of deciding which lots you get if you come top in more than the maximum.
Are lots evaluated separately?
Yes. Award criteria are set for each lot and the buyer awards each lot to the most advantageous tender for that lot. Winning one lot does not help or hurt your score on another, unless the documents set out a rule for awarding several lots to the same supplier.
Do the same rules apply to contracts that started under the old regulations?
No. Procurements that began under the Public Contracts Regulations 2015, including call-offs from frameworks set up under them, continue under those rules. Regulation 46 of the 2015 rules covered lots in a similar way, but reasons for not splitting could be kept in the procurement documents or the buyer's internal report.