Guide

The Procurement Act 2023 explained for suppliers

The Procurement Act 2023 replaced the old EU-derived procurement regulations on 24 February 2025. For suppliers it changed where you register, how tenders are run, what you are told when you lose, how suppliers can be excluded, and how much is published after a contract is signed. This is the supplier's summary, with every point linked to the Act itself.

Last checked: 7 October 2026

At a glance
Royal Assent26 October 2023
In force24 February 2025, for procurements started from that date
WhereEngland, Wales and Northern Ireland. Scotland keeps its own law
Size128 sections and 11 schedules as enacted, since amended
Where notices goFind a Tender, the government's Central Digital Platform

The full text is on legislation.gov.uk, and the government publishes guidance on each part. Our tender jargon glossary explains the new terms in a line each.

1. One platform, one set of details

Every procurement under the Act is published on Find a Tender, which is now the Central Digital Platform. You register there once, keep your core supplier information up to date (who you are, your legal form, financial standing, connected persons and exclusion grounds), and give buyers a share code instead of filling in the same details for every tender. The questions specific to a procurement come in a standard Procurement Specific Questionnaire, which replaced the old selection questionnaire. What you need before you bid covers the registration step by step.

Each stage of a procurement now has its own numbered notice:

NoticePublished when
UK1 PipelineA buyer expecting to spend over £100m in the year lists what it plans to buy
UK2 Preliminary market engagementThe buyer is talking to the market before a tender
UK3 Planned procurementAdvance notice of a tender, which can shorten the tender period
UK4 TenderThe competition opens
UK5 TransparencyBefore a direct award without competition
UK6 Contract awardThe buyer names the intended winner; standstill starts
UK7 Contract detailsThe contract is signed
UK9 Contract performancePerformance against key performance indicators, at least yearly
UK10 Contract changeBefore a significant change to value, term or supplier
UK11 and UK12 TerminationA contract ends (UK11) or a procurement is cancelled (UK12)
UK13 to UK16 Dynamic marketA dynamic market is planned, set up, changed or closed
UK17 Payments complianceHow promptly the buyer pays its invoices

Source: Find a Tender, notice types. Watching UK2 and UK3 notices is the easiest way to hear about a tender early: finding contracts before they are re-tendered explains how.

2. Two procedures instead of many

A buyer runs either an open procedure, a single stage that anyone can bid in, or a competitive flexible procedure that it designs itself, with shortlisting, negotiation or several rounds if it chooses (section 20). The old restricted procedure, competitive dialogue and competitive procedure with negotiation no longer exist, though a buyer can design something similar. The competitive flexible procedure explained covers what to expect. Contracts can still be awarded directly without competition, but only on grounds the Act lists, and after a transparency notice (section 41, section 44, Schedule 5).

Minimum time to respond

Tender periodMinimum
Electronic tenders, all documents provided at the start25 days
Electronic but not all documents at the start, or paper with all documents30 days
Neither35 days
After a qualifying planned procurement notice, or in urgency10 days
Requests to participate in a competitive flexible procedure25 days (10 in urgency)

Calendar days, from section 54, which also requires buyers to consider the complexity of the work, site visits and subcontracting, and to give every supplier the same time. Light touch contracts have no minimum.

3. Who can bid: conditions of participation

The old selection stage is replaced by conditions of participation, limited to legal and financial capacity and technical ability, and proportionate to the contract (section 22). Three protections matter to small firms: a buyer cannot demand audited accounts from a supplier not legally required to have them, cannot require contract insurance to be in place before award, and cannot require you to have held a previous contract with it. Buyers must also have regard to the barriers small and medium-sized enterprises face (section 12).

4. How the winner is chosen, and what losers are told

Contracts go to the most advantageous tender, judged against published award criteria and an assessment methodology (section 19, section 23). Before announcing the winner, the buyer sends every assessed bidder an assessment summary with its own scores and the winner's (section 50), then publishes the contract award notice, which starts an eight working day standstill (section 51). How to write a tender response that scores and getting feedback when you lose cover both sides.

5. Exclusions and the debarment list

The Act sets out when a supplier must or may be excluded. A supplier is excluded when a mandatory ground applies (Schedule 6), such as fraud, bribery, modern slavery offences, serious tax misconduct or a threat to national security, and the circumstances are continuing or likely to happen again. It is excludable on the same test for a discretionary ground (Schedule 7), such as insolvency, professional misconduct, or breach of contract and poor performance (section 57).

  • Time limits. Events more than five years old are ignored, and for some discretionary grounds, including breach of contract and poor performance, three years.
  • Putting it right. Before excluding you, a buyer must give you a reasonable chance to show what you have done about it, such as changing staff or management or bringing in new procedures and training (section 58).
  • The debarment list. A minister can add a supplier to a published debarment list after an investigation, with appeal to the court (sections 62 to 65). Investigations are run by the Debarment Review Service, part of the Government Commercial Agency since 1 April 2026. The list published in November 2025 was blank, and remains so until a supplier is added.

6. After the contract is signed

Much more is now published during the life of a contract, and some of it can count against a supplier later.

  • Key performance indicators. Contracts over £5 million must have at least three, assessed and published at least once a year (section 52, section 71).
  • Poor performance. Where a supplier fails to improve after a proper opportunity, or a breach leads to termination, damages or a settlement, the buyer must publish it within 30 days (section 71). That record can support exclusion from future procurements.
  • Changes. Significant changes to a contract's value, term or supplier need a contract change notice first; smaller changes, up to 10% of value for goods and services, 15% for works or 10% of the term, do not (sections 74 and 75).
  • Publication. Contracts over £5 million are published, with sensitive commercial information withheld only where there is an overriding public interest (section 53, section 94).
  • Payment. Valid, undisputed invoices must be paid within 30 days, and the same term passes down to subcontracts (section 68, section 73).

7. Frameworks, dynamic markets and smaller contracts

Frameworks run for up to four years (eight for defence and utilities), and open frameworks, which must reopen to new suppliers, can run for up to eight in total. Dynamic markets replace dynamic purchasing systems and stay open for suppliers to join throughout. What is a framework agreement? covers both. Below the thresholds, buyers that invite tenders cannot shortlist on capacity first, and must publish notices for contracts they advertise from £12,000 (central government) or £30,000 (other buyers), including VAT: procurement thresholds 2026 has the figures.

8. Challenging a decision

A supplier that has suffered, or risks suffering, loss from a breach of the Act can bring proceedings in court (section 100). Issuing a claim during standstill, and telling the buyer, stops the contract being signed until the court decides (section 101). Claims must generally be brought within 30 days of when you knew or ought to have known of the breach (section 106), and a court can set a contract aside or award damages. Take legal advice quickly: the time limits are short. The Cabinet Office's Public Procurement Review Service also looks into supplier concerns without going to court.

What has not changed

Buyers still publish their opportunities, still score against published criteria, and still cannot treat suppliers unequally (section 12). The Act made the process more transparent, particularly for small firms, but winning still comes down to choosing the right tenders and answering the question asked. How to bid for public sector contracts is the place to start.

Every notice under the new Act, in one email

Under the Procurement Act, pipeline, tender and contract notices all go to Find a Tender. Tender Radar reads them, with the other three UK portals, every weekday and sends you the ones that fit. 30 days free, no card needed.

Common questions

The Procurement Act 2023

When did the Procurement Act 2023 come into force?

On 24 February 2025. It received Royal Assent on 26 October 2023. Procurements started before 24 February 2025 continue under the old regulations, such as the Public Contracts Regulations 2015, until they finish.

Does the Procurement Act 2023 apply in Scotland?

Not to Scottish devolved bodies, which follow their own procurement law, the Procurement Reform (Scotland) Act 2014 and the Public Contracts (Scotland) Regulations 2015. It applies in England, Wales and Northern Ireland, with Welsh devolved authorities following it alongside the Procurement (Wales) Regulations 2024.

What are the main changes in the Procurement Act 2023 for suppliers?

One central platform (Find a Tender) where you register once and share your details with a code; two procedures (open and competitive flexible) instead of several; conditions of participation in place of selection questionnaires; an assessment summary for every assessed bidder showing the winner's scores; new rules on excluding and debarring suppliers; and more published information after award, including performance against key performance indicators on contracts over £5 million.

What is the debarment list?

A public list, kept by a Minister of the Crown, of suppliers that buyers must or may exclude because an exclusion ground applies to them. Suppliers can apply for removal and appeal to the court. The list published in November 2025 had no suppliers on it, and remains blank until a minister decides to add one after an investigation.

How long does a buyer have to give for a tender under the Procurement Act?

At least 25 days for tenders submitted electronically with all documents available from the start, 30 or 35 days in other cases, and as little as 10 days where a planned procurement notice was published or in urgency. Requests to participate in a competitive flexible procedure have at least 25 days. Buyers must also consider the complexity of the work.