London Gateway - Second Rail Terminal Phase 2

London Gateway Port Limited awarded this to Trackwork Limited for £31.0m, running to 19 Mar 2028.

£31.0m
Value
19 Mar 2028
Runs until
1
Supplier

Find tenders for your company

Paste your website and we score this week’s UK public sector tenders against it, each with a reason. Then start your free month with those matches.

Already know you want it? Start your free month

Who won

What is being bought

Description

DP World is undertaking the expansion of its London Gateway Port facility at Stanford le

Hope, through the development of a new second rail terminal located to the west of the

existing eastern operational rail facility. This investment will significantly increase the

port's rail freight capacity, improve operational resilience, and support the continued

growth of DP Worlds sustainable, low carbon logistics solutions.

This expansion represents a strategic enhancement of the port's intermodal capability,

Read the full description

enabling faster, more efficient movement of goods across the UK and supporting national

objectives for greener freight transport. The new terminal will play a key role in

accommodating future demand and maintaining London Gateway's position as a world

class logistics and supply chain hub.

The Scope of Works covered under this tender include, but are not limited to, the following

key elements:

Permanent Way Works

Construction of new railway infrastructure to serve the second terminal including plain line

track, and associated components in a phase installation sequence delivering five new

sidings (7 to 11) to compliment the two sidings (12 and 13) already constructed during Phase 1/1A of the works, which are currently in operation. Installation and integration of

21 new switches and crossings (S&C) required to connect the new terminal to the existing

rail network corridor as well as providing more route paths for trains entering and exiting

the existing eastern rail terminal.

Civil Engineering Works

Installation of a circa 850m long reinforced concrete crane rail beam with pre-cast

concrete pile foundations and its associated mechanical chambers to allow Rail Mounted

Gantry Crane (RMGC) operations within the new terminal. Earthworks, formation

preparation, track drainage and utility diversions necessary to support the new terminal

infrastructure. Construction of numerous ancillary civils foundation bases, walkways,

cable routes and under track crossings for the new signalling, telecommunications and

electrical plant equipment, shunters cabin and REB building.

Telecommunications Works

Installation of new and relocation of existing Operational Telecoms and SiSS systems

assets including CCTV cameras, signal post and point zone telephones and the shunters

panel concentrator.

Signaling Works

Provision of new and relocation of existing signaling assets, including lineside equipment,

control system modifications in the form of new Shunters Cabin housing an updated

control panel to operate both rail terminals, and associated REB for the signaling system

interlocking. These assets will be constructed in a staged delivery to align with the

permanent way phasing, to ensure full operational compatibility. Installation of new

signaling track circuits to both the western and eastern terminals will enable operation of

both facilities from the one new control panel. Testing, commissioning and integration of

all new rail systems with existing operational infrastructure as well as update to the

Upminster IECC workstation screens.

Electrical and Plant Works

New power supplies to the various disciplines line side equipment, shunters cabin and

REB, as well as new points heating assets for both the western and existing eastern rail

terminal S&C units.

Interfaces and Integration

Management of all interfaces with existing rail infrastructure, port operations, utilities, and

third party stakeholders. Development of staging plans to minimise operational disruption

and ensure safe working adjacent to live rail and port environments. Coordination with existing port operations to ensure safe and continuous functionality during construction.

Project Goals

Upon completion, the new rail terminal will provide; increased rail served capacity for

containerised freight, enhanced operational flexibility and resilience, deliver infrastructure

capable of supporting robotic next generation RMGC equipment and improved efficiency

as well as reduce the ports carbon impact through expanded rail freight capability.

London Gateway Port Limited

Since 2021, London Gateway Port Limited has awarded 1 contract in this category, worth £31.0m across the 1 that published a value.

Everything London Gateway Port Limited buys

Similar contracts coming back to market

Contracts in the same category at other buyers, ending in the next 18 months.

Every official notice

  1. 23 Nov 2026

    Contract awarded110675-2026
How to cite this data

Tender Radar (2026) London Gateway - Second Rail Terminal Phase 2: London Gateway Port Limited [Dataset]. Professor AI. Available at: https://tender-radar.co.uk/contracts/ocds-h6vhtk-066c43 (Accessed: 26 November 2026).

The figures change as notices are published, so the citation carries the date you read them.

From Find a Tender, published under the Open Government Licence v3.0. Always check the official notice before bidding. Contract reference ocds-h6vhtk-066c43.