Running until 31 Dec 2026

Sharnberry MWTS - Power Connection - Phase 2 Non-Contestable Works

Mining Remediation Authority awarded this to Northern Powergrid (Northeast) PLC for £435k, running to 31 Dec 2026.

£435k
Value
31 Dec 2026
Runs until
1
Supplier

Find tenders for your company

Paste your website and we score this week’s UK public sector tenders against it, each with a reason. Then start your free month with those matches.

Already know you want it? Start your free month

Who won

  • Northern Powergrid (Northeast) PLC

    Companies House 02906593 · 2 other contracts with Mining Remediation Authority since 2021

What is being bought

The Water and Abandoned Metal Mines Programme (WAMM) is the primary delivery mechanism to achieve the statutory Environment Act target to halve the length of rivers polluted by harmful metals from abandoned metal mines by 2038.

WAMM is being delivered by a partnership between the Mining Remediation Authority, the Environment Agency and Defra.

The former Sharnberry mines are located in County Durham at the far eastern edge of the North Pennines Orefield, in the Pennines Moors.

The mines pollute rivers in the Wear catchment, specifically the Euden Beck and downstream Bedburn Beck.

Read the full description

The Environment Agency carried out a detailed monitoring programme to measure the metal concentrations and river flows at various points across the catchment. This monitoring indicated that the Sharnberry adit is the most significant source of zinc and cadmium pollution and also contributes to lead pollution.

The Environment Agency have advised that a Mine Water Treatment Scheme (MWTS) is required that will require a permanent power connection.

In February 2025, it was agreed to progress with Phase 1 of the grid connection, which is from Eggleston Crest to the boundary of the Eggleston Estate access track.

This contract is for non-contestable works of the phase 2 grid extension, which is for Northern Powergrid to:

- Upgrade the existing two-conductor system to Three-Phase, which involves rebuilding the line.

- Carrying out 1x HV closing joint

- Undertaking all Senior Authorised Person work associated with all connections to the Distribution System

Mining Remediation Authority

Since 2021, Mining Remediation Authority has awarded 1 contract in this category, worth £435k across the 1 that published a value.

Everything Mining Remediation Authority buys

Similar contracts coming back to market

Contracts in the same category at other buyers, ending in the next 18 months.

How to cite this data

Tender Radar (2026) Sharnberry MWTS - Power Connection - Phase 2 Non-Contestable Works: Mining Remediation Authority [Dataset]. Professor AI. Available at: https://tender-radar.co.uk/contracts/ocds-h6vhtk-0615cf (Accessed: 27 November 2026).

The figures change as notices are published, so the citation carries the date you read them.

From Find a Tender, published under the Open Government Licence v3.0. Always check the official notice before bidding. Contract reference ocds-h6vhtk-0615cf.