Sharnberry MWTS - Power Connection - Phase 2 Non-Contestable Works
Mining Remediation Authority awarded this to Northern Powergrid (Northeast) PLC for £435k, running to 31 Dec 2026.
- £435k
- Value
- 31 Dec 2026
- Runs until
- 1
- Supplier
Find tenders for your company
Paste your website and we score this week’s UK public sector tenders against it, each with a reason. Then start your free month with those matches.
Who won
- Northern Powergrid (Northeast) PLC
Companies House 02906593 · 2 other contracts with Mining Remediation Authority since 2021
What is being bought
The Water and Abandoned Metal Mines Programme (WAMM) is the primary delivery mechanism to achieve the statutory Environment Act target to halve the length of rivers polluted by harmful metals from abandoned metal mines by 2038.
WAMM is being delivered by a partnership between the Mining Remediation Authority, the Environment Agency and Defra.
The former Sharnberry mines are located in County Durham at the far eastern edge of the North Pennines Orefield, in the Pennines Moors.
The mines pollute rivers in the Wear catchment, specifically the Euden Beck and downstream Bedburn Beck.
Read the full description
The Water and Abandoned Metal Mines Programme (WAMM) is the primary delivery mechanism to achieve the statutory Environment Act target to halve the length of rivers polluted by harmful metals from abandoned metal mines by 2038.
WAMM is being delivered by a partnership between the Mining Remediation Authority, the Environment Agency and Defra.
The former Sharnberry mines are located in County Durham at the far eastern edge of the North Pennines Orefield, in the Pennines Moors.
The mines pollute rivers in the Wear catchment, specifically the Euden Beck and downstream Bedburn Beck.
The Environment Agency carried out a detailed monitoring programme to measure the metal concentrations and river flows at various points across the catchment. This monitoring indicated that the Sharnberry adit is the most significant source of zinc and cadmium pollution and also contributes to lead pollution.
The Environment Agency have advised that a Mine Water Treatment Scheme (MWTS) is required that will require a permanent power connection.
In February 2025, it was agreed to progress with Phase 1 of the grid connection, which is from Eggleston Crest to the boundary of the Eggleston Estate access track.
This contract is for non-contestable works of the phase 2 grid extension, which is for Northern Powergrid to:
- Upgrade the existing two-conductor system to Three-Phase, which involves rebuilding the line.
- Carrying out 1x HV closing joint
- Undertaking all Senior Authorised Person work associated with all connections to the Distribution System
Mining Remediation Authority
Since 2021, Mining Remediation Authority has awarded 1 contract in this category, worth £435k across the 1 that published a value.
Everything Mining Remediation Authority buysSimilar contracts coming back to market
Contracts in the same category at other buyers, ending in the next 18 months.
- 260019 Temporary Sound, Lighting and Audio-Visual Services
Queen's University Belfast · held by Moonlighting AV (NI) Limited · £400k · ends 30 Sept 2027
- EV Charging Phase 2
National Highways · held by Mer Fleet Services Limited · £321k · ends 21 Oct 2027
- PRE00145 AV Solution for Baltic Room
Pool Re Services Limited · held by Project Audio Visual Ltd · £36k · ends 9 Oct 2027
- UPS Units and Design/Layout of the Devices - AWARD
Sandwell Metropolitan Borough Council · held by Data Power Ltd · £98 · ends 1 Feb 2028
How to cite this data
Tender Radar (2026) Sharnberry MWTS - Power Connection - Phase 2 Non-Contestable Works: Mining Remediation Authority [Dataset]. Professor AI. Available at: https://tender-radar.co.uk/contracts/ocds-h6vhtk-0615cf (Accessed: 27 November 2026).
From Find a Tender, published under the Open Government Licence v3.0. Always check the official notice before bidding. Contract reference ocds-h6vhtk-0615cf.