CPSP 143 A303 Stonehenge (Tunnel ERA)

Highways England Company Limited awarded this to Benchmark Estimating for £19k, running until 31 Mar 2021.

£19k
Value
31 Mar 2021
Ended
1
Supplier

Find tenders for your company

Paste your website and we score this week’s UK public sector tenders against it, each with a reason. Then start your free month with those matches.

Already know you want it? Start your free month

Who won

What is being bought

The A303 Stonehenge project has been asked to investigate the impacts of adding emergency refuges or an additional hard shoulder within in the Stonehenge tunnel in order to increase tunnel safety over the 3km bored tunnels. This requires an assessment of the incremental cost and schedule versus the current baseline scheme (D2AP tunnel without refuges or hard shoulder).

Two options are to be considered:

Read the full description

- The provision of two lay-byes per tunnel, spaced at 1000m centres (four in total), constructed using SCL techniques, to provide an emergency refuge during traffic emergencies / incidents.

- Increasing the diameter of the tunnels to incorporate a hard shoulder lane over the entire length of the tunnel

The incremental cost and schedule impacts are to be measured vs the current baseline scheme design. This will require establishing a baseline estimate and schedule with a consistent set of assumptions against which the above options can be compared. The assessment is to include development of design and methodology assumptions in consultation with the A303 Stonehenge project team so that the assessment has a robust design, methodology and schedule basis.

The assessment is to include the following activities

- Mobilisation and collection of reference design information for the baseline scheme and definition of the above options

- Confirm scope of assessment and output requirements with the A303 Stonehenge project

- Establishment of cost and schedule estimate for the baseline scheme

- Identification of design and construction methodology for the emergency refuge option

- Identification of design and construction methodology for the emergency refuge option

- Production of cost estimates and outline schedule for each option

- Comparison with baseline scheme and identification of incremental impacts

- Production of report to capture impacts and the design / methodology assumptions. This is to include commentary on risks to delivery of the options.

- Presentation of findings

No design cross sections are available for the above options at this time and these are to be developed as part of the assessment. The level of detail within the assessment should be commensurate a concept design / PCF Options Stage 1 level.

Highways England Company Limited

Since 2021, Highways England Company Limited has awarded 10 contracts in this category, worth £492k across the 10 that published a value.

Everything Highways England Company Limited buys

Similar contracts coming back to market

Contracts in the same category at other buyers, ending in the next 18 months.

How to cite this data

Tender Radar (2026) CPSP 143 A303 Stonehenge (Tunnel ERA): Highways England Company Limited [Dataset]. Professor AI. Available at: https://tender-radar.co.uk/contracts/ocds-b5fd17-c7690960-cc59-4127-b721-1fe68fecac72 (Accessed: 27 November 2026).

The figures change as notices are published, so the citation carries the date you read them.

From Contracts Finder, published under the Open Government Licence v3.0. Always check the official notice before bidding. Contract reference ocds-b5fd17-c7690960-cc59-4127-b721-1fe68fecac72.